It's been a busy week in our new office space. In just the past week, all this has happened:
- All our ethernet cables, HDMI cables, and speaker wire have been run in the new space
- Cable ends and wall plates are installed
- Finish coats of paint are up on all the walls, including the new blue wall
- Speakers and projector mounts are up in the new conference room ceiling
- The remaining adhesive has been scraped off the floor
- All the ceiling tiles have been cut and installed
- The temporary wall came down, then was replaced by a temporary curtain
The carpet will be installed next week, and today, they're cleaning all the storefront glass - a sure sign that the project is nearly complete.